Same scope across bids, realistic allowances, every sheet priced, named products, payments tied to progress, and a contractor you have verified with L&I.

Nov 20, 2026

How to Read a Builder's Bid

Most people read a bid from the bottom: they look at the total and pick the lowest. The total tells you little until you know what stands behind it. Here is what to check before you sign.

Line up the scope before the totals

Two bids can only be compared if they price the same work. The lowest number is often low not because the contractor is more efficient, but because part of the job is missing. No footing drains, no haul-off of excavated soil, no gutters and downspouts, no landscaping restoration after the trucks leave.

Start with the scope. Put the bids side by side and go division by division: site work, foundation, framing, roofing, windows and doors, plumbing, electrical, mechanical, insulation, drywall, finishes, exterior. Mark what each one leaves out or lists as excluded. Read the exclusions page as carefully as the price page. The cleanest comparison comes when every contractor prices the same set of construction documents: then the quantities match and what remains is price.

Allowances: where the price is still open

Every bid has items that are not fully chosen at signing: tile, plumbing fixtures, lighting, appliances, cabinet hardware. They usually appear as allowances, a sum set aside for that item. That is normal, and it is exactly where bids differ most.

Check two things. First, how many allowances there are and how large a share of the bid they make up. Second, whether the sums are realistic. If the design calls for a specific tile and the allowance would not buy it, the bid only looks cheaper on paper. You will pay the difference later. Compare each allowance against the specifications in the drawings and against the price of the products you actually want. Also ask how overruns are handled: whether the contractor adds a markup on the amount above the allowance.

Every sheet priced, every product named

Go through the construction set sheet by sheet and find each one in the bid. What gets dropped is usually what you cannot see from the street:

  • Site work: clearing, grading, excavation and haul-off, erosion control, driveway.
  • Drainage: footing drains, downspout connections, stormwater measures the permit requires.
  • Structural details: hold-downs, shear walls, beams and connectors from the structural sheets.
  • Energy items: insulation levels, air sealing, ventilation and heat pump equipment, the energy code measures noted on the plans.
  • Utilities: water, sewer or septic, power from the street to the house.

Then look at how materials are described. A line that says "windows, vinyl, or equal" lets almost anything through. Two windows that look the same can differ widely in frame, glass and hardware. A good bid names the product: manufacturer, series or model, key performance figures. If the contractor wants room to substitute, write into the contract that any substitution needs your written approval and must perform at least as well.

Before you sign: contract, payments, L&I

Get every bid in writing, and sign a written contract that includes the scope, the drawings it is based on, the allowances, how change orders are priced and approved, and the payment schedule. A price agreed on the phone is not something anyone can be held to.

Tie payments to completed and accepted work, not to dates on a calendar. Foundation poured and inspected, hidden work recorded, then the foundation payment. A large deposit for the whole job removes the contractor's main reason to keep moving. A deposit for the materials of a specific stage is easy to verify: the materials are either on site or they are not.

In Washington State, contractors must be registered with the Department of Labor and Industries (L&I) under RCW 18.27.020. Before you sign, look the contractor up on the L&I website: check that the registration is active, that the business name matches the one on the bid and the contract, and what insurance information is on file. Ask for a certificate of general liability insurance as well. A few minutes of checking can save a great deal of trouble.

How construction to a design is priced, DeZZign explains on its Construction page; how materials are chosen and bought against the specification, in Material Selection.

How LINKS does it

LINKS prices estimates from the drawings and specifications before work starts: quantities, materials, timing. In the US, bids are priced against the construction drawings, and the work on site is done by contractors registered in Washington State, with general liability insurance, people we have worked with. When we help compare bids, we check that they price the same scope, which items are allowances and whether those sums are realistic, and that every sheet is priced: site work, drainage, structural details, energy items.

When we also handle procurement, the purchase schedule is tied to the stages of work, and partner discounts range from 10 to 40% depending on the item. We build in the Seattle area and in Ukraine.